January, 2015 | ||
Description:"THE CONSTRUCTION PROJECT OF BUILDING THE NEW SYSTEM OF SPURS LOCATED ON ASHORE OF HEL PENINSULA - KM 0.0 - 12.3"
Investor:Treasury - Director of Maritime Office in Gdynia |
|
On behalf of the Maritime Office in Gdynia we made a design project of the new system of spurs on part of the edge of the Hel Peninsula, which is in danger of erosion processes - from the Wladyslawowo Port (km 0.0) to the Kuznica (km 12.3).
The proposed system consists of 119 pieces of spurs, 100 m length each, and 16 units of 20 to 95 m length. It is made from piles of wood with diameter of approx. 30 cm and a length of 4 to 10 m. The total number of piles to drive is 31,518. To protect the shore, the project provides the restoration on the beach on discussed section of the coast - to a minimum width of 40 m (distance from the base of the dunes to the shoreline). The beach with spurs will be a comprehensive form of protection of the sea coast and sand dunes.
The project will be realized in several stages. Each stage has been included in a separate volume of the construction project.
|