November, 2015 | ||
Description:"REPAIRING AND RECONSTRUCTION OF THE COASTAL PROTECTION IN GDYNIA OKSYWIE (km 89.00÷90.70)"
Investor:Director of Maritime Office in Gdynia |
|
The investment in the Oksywie area had been realised from July 2014 and it took 1.5 year to finish it. The protective structure of the cliff is approx. 1,700 m long and it is a part of Kepa Oksywska – from Gdynia’s Port of War to the north, towards the Fisherman Settlements. According to the project, along the constructions there is a footpath which is called now: ”The Second Gdynia Boulevard”. We would like to invite you to walk.
We wrote more about this project in July, 2015 → read here
Photos of the next stages of building are to be found on the website of Maritime Office in Gdynia → watch here
Below current pictures of the buildings: |